Home
Class 14
MATHS
A can do a piece of work in 15 days and ...

A can do a piece of work in 15 days and B is 25% more efficient than A. If A and B both work for 4 days and after 4 days C can complete the remaining work alone in 8 days, then find time taken by A, B and C together to complete the whole work.

A

6 days

B

5 days

C

8 days

D

10 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will follow the logical sequence outlined in the video transcript. ### Step 1: Determine the work done by A A can complete the work in 15 days. Therefore, the work done by A in one day is: \[ \text{Work done by A in 1 day} = \frac{1}{15} \text{ of the total work} \] ### Step 2: Determine the efficiency of B B is 25% more efficient than A. If A's efficiency is represented as 100%, then B's efficiency is: \[ \text{Efficiency of B} = 100\% + 25\% = 125\% \] This means B can do the work in fewer days. To find the time taken by B: \[ \text{Time taken by B} = \frac{100}{125} \times 15 = 12 \text{ days} \] Thus, the work done by B in one day is: \[ \text{Work done by B in 1 day} = \frac{1}{12} \text{ of the total work} \] ### Step 3: Calculate the total work To find the total work, we can use the least common multiple (LCM) of the days taken by A and B: \[ \text{LCM of 15 and 12} = 60 \text{ units of work} \] ### Step 4: Calculate the daily work of A and B Now we can calculate the work done by A and B in one day: - Work done by A in one day = \( \frac{60}{15} = 4 \) units - Work done by B in one day = \( \frac{60}{12} = 5 \) units ### Step 5: Calculate the work done by A and B in 4 days In 4 days, A and B together will do: \[ \text{Total work done by A and B in 4 days} = (4 + 5) \times 4 = 9 \times 4 = 36 \text{ units} \] ### Step 6: Determine the remaining work The remaining work after A and B have worked for 4 days is: \[ \text{Remaining work} = 60 - 36 = 24 \text{ units} \] ### Step 7: Determine the efficiency of C C can complete the remaining work in 8 days, so the work done by C in one day is: \[ \text{Work done by C in 1 day} = \frac{24}{8} = 3 \text{ units} \] ### Step 8: Calculate the combined efficiency of A, B, and C Now, we can find the combined efficiency of A, B, and C: \[ \text{Combined efficiency} = 4 + 5 + 3 = 12 \text{ units per day} \] ### Step 9: Calculate the time taken by A, B, and C together to complete the whole work To find the time taken by A, B, and C together to complete the entire work of 60 units: \[ \text{Time taken} = \frac{60}{12} = 5 \text{ days} \] ### Final Answer The time taken by A, B, and C together to complete the whole work is **5 days**. ---
Promotional Banner