A, B and C can complete a piece of work ...

A, B and C can complete a piece of work in 4, 28 and 56 respectively. Working together, they can complete the same work in how many days ?

A

`5 5/17`

B

`3 1/17`

C

`5 1/17`

D

`3 5/17`

Text Solution

Verified by Experts

The correct Answer is:
D
Promotional Banner

Similar Questions

Explore conceptually related problems

A, B and C can complete a piece of work in 4, 28 and 56 days respectively. Working together, they can complete the same work in how many days? A, B और C किसी काम को क्रमशः 4, 28 और 56 दिनों में पूरा कर सकते हैं| एक साथ मित्रकर काम करने पर, वे उसी काम को कितने दिनों में पूरा कर सकेंगे?

A, B and C can complete a piece of work in 10, 20 and 60 days respectively. Working together they can complete the same work in how many days?

A B and C can complete a piece of work in 24, 6 and 12 days respectively. They will complete the same work in :

The capacities of A,B and C to complete a piece of work is 1:2:3 . By working together, the thre of them can complete the work in 24 days. In how many days can C alone complete it ?