If 27 people, working 8 hours a day, can...

If 27 people, working 8 hours a day, can complete a task in 12 days, then in how many days will 18 people finish the task, working 9 hours a day?

A

15 days

B

16 days

C

18 days

D

20 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem, we can use the work formula, which states that: \[ \text{Work} = \text{Men} \times \text{Days} \times \text{Hours} \] Given: - \( m_1 = 27 \) (people) - \( d_1 = 12 \) (days) - \( h_1 = 8 \) (hours) - \( m_2 = 18 \) (people) - \( h_2 = 9 \) (hours) - \( d_2 \) = ? (days) Since the work done is the same in both cases, we can set up the equation: \[ m_1 \times d_1 \times h_1 = m_2 \times d_2 \times h_2 \] Substituting the known values into the equation: \[ 27 \times 12 \times 8 = 18 \times d_2 \times 9 \] Now, we can simplify this equation step by step. 1. Calculate the left side: \[ 27 \times 12 = 324 \] \[ 324 \times 8 = 2592 \] 2. Now, substitute this value back into the equation: \[ 2592 = 18 \times d_2 \times 9 \] 3. Simplify the right side: \[ 18 \times 9 = 162 \] Thus, we have: \[ 2592 = 162 \times d_2 \] 4. To find \( d_2 \), divide both sides by 162: \[ d_2 = \frac{2592}{162} \] 5. Now, calculate \( d_2 \): \[ d_2 = 16 \] So, the number of days \( d_2 \) that 18 people will take to finish the task working 9 hours a day is **16 days**.
Promotional Banner

Similar Questions

Explore conceptually related problems

Working 7 hours a day, 18 persons can complete a certain work in 32 days. In how many days would 14 persons complete the same work, working 8 hours a day ?

15 persons working 8 hours a day can complete a work in 21 days.How many days will 14 persons take to complete a work 1(1)/(2) xx as great,if they work 6 hours a day?

30 men working 5 hours a day can do a task in 16 days in how many days will 40 men working 6 hours a day fo the same task ? A. 12 days B. 10 days C. 15 days D. 18 days

Recommended Questions
  1. If 27 people, working 8 hours a day, can complete a task in 12 days, t...

    Text Solution

    |

  2. 8 पुरुष 9 घंटे प्रतिदिन काम करके एक काम को 20 दिनों में ख़त्म ...

    Text Solution

    |

  3. 639 व्यक्ति 5 घंटे प्रतिदिन काम करके 12 दिनों में एक सड़क की मरम्...

    Text Solution

    |

  4. 5 व्यक्ति 7 घण्टे प्रतिदिन काम करके एक नामांकन सूची 8 दिनों में त...

    Text Solution

    |

  5. यदि 80 व्यक्ति किसी काम को 6 घंटे प्रतिदिन काम करके 16 दिनों...

    Text Solution

    |

  6. 15 आदमी 8 घंटे प्रतिदिन काम करके 20 दिनों में काम पूरा कर सकता ...

    Text Solution

    |

  7. यदि 90 आदमी प्रतिदिन 12 घंटे काम करके किसी काम को 16 दिन में पूरा कर ...

    Text Solution

    |

  8. एक दिन में 7 घंटे कार्य करने पर 4 व्यक्ति किसी कार्य को 8 दिन में...

    Text Solution

    |

  9. 5 व्यक्ति 6 दिनों तक 6 घंटे प्रतिदिन कार्य करके 10 खिलोने तैयार कर सकत...

    Text Solution

    |