Home
Class 14
MATHS
P and Q can finish a work in 10 days and...

P and Q can finish a work in 10 days and 5 days, respectively. Q worked for 2 days and left the job. In how many days can P alone finish the remaining work?

A

10 days

B

6 days

C

4 days

D

8 days

Text Solution

Verified by Experts

The correct Answer is:
B
Promotional Banner

Similar Questions

Explore conceptually related problems

A can finish a work in 18 days and B can do the same work in 15 days. B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?

A can finish a work in 18 days and B can do the same work in 15 days B worked for 10 days and left the job. In how many days, A alone can finish the remaining work? (A) 5 (B) 5 (D) 8 (C) 6

Rakesh and Siva can do a piece of work in 15 days and 18 days respectively. They work together for 5 days and then Rakesh leaves. In how many days will Siva alone finish the remaining work?

Rakesh and Siva can do a piece of work in 15 days and 18 days respectively. They work together for 5 days and then Rakesh leaves. In how many days will Siva alone finish the remaining work?

A can do a piece of work in 15 days and B alone can do it in 10 days. B works at it for 5 days and then leaves. In how many days, A alone can finish the remaining work?

A and B can do a job in 15 days and 10 days, respectively. They began the work together but A leaves after some days and B finished the remaining job in 5 days. After how many days did A leave?