Home
Class 14
MATHS
P can complete a work in 15 days and Q i...

P can complete a work in 15 days and Q in 24 days. They began the work together, but Q left the work 2 days before its completion. In how many days, was the work completed?

A

8

B

10

C

9

D

11

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we can follow these calculations: ### Step 1: Determine the work done by P and Q in one day - P can complete the work in 15 days, so the work done by P in one day is: \[ \text{Work done by P in one day} = \frac{1}{15} \text{ of the work} \] - Q can complete the work in 24 days, so the work done by Q in one day is: \[ \text{Work done by Q in one day} = \frac{1}{24} \text{ of the work} \] ### Step 2: Find the combined work done by P and Q in one day - To find the combined work done by P and Q in one day, we can add their individual work rates: \[ \text{Combined work rate} = \frac{1}{15} + \frac{1}{24} \] - To add these fractions, we need a common denominator. The LCM of 15 and 24 is 120. Thus: \[ \frac{1}{15} = \frac{8}{120} \quad \text{and} \quad \frac{1}{24} = \frac{5}{120} \] - Therefore, \[ \text{Combined work rate} = \frac{8}{120} + \frac{5}{120} = \frac{13}{120} \] ### Step 3: Calculate the total work done before Q leaves - Let \( x \) be the number of days they worked together before Q leaves. Since Q leaves 2 days before the work is completed, P works alone for 2 days after Q leaves. - In \( x \) days, the total work done by both P and Q is: \[ \text{Work done together} = x \times \frac{13}{120} \] - In the 2 days that P works alone, the work done is: \[ \text{Work done by P alone} = 2 \times \frac{1}{15} = \frac{2}{15} \] ### Step 4: Set up the equation for total work - The total work is equal to 1 (the whole work), so we can set up the equation: \[ x \times \frac{13}{120} + \frac{2}{15} = 1 \] ### Step 5: Solve for \( x \) - First, convert \(\frac{2}{15}\) to a fraction with a denominator of 120: \[ \frac{2}{15} = \frac{16}{120} \] - Now, substitute back into the equation: \[ x \times \frac{13}{120} + \frac{16}{120} = 1 \] - Multiply through by 120 to eliminate the denominator: \[ 13x + 16 = 120 \] - Rearranging gives: \[ 13x = 120 - 16 = 104 \] - Solving for \( x \): \[ x = \frac{104}{13} = 8 \] ### Step 6: Calculate the total time taken to complete the work - Since they worked together for 8 days and P worked alone for 2 days: \[ \text{Total time} = 8 + 2 = 10 \text{ days} \] ### Final Answer: The work was completed in **10 days**. ---
Promotional Banner

Similar Questions

Explore conceptually related problems

A can do a piece of work in 18 days and B in 12 days. They began the work together, but B left the work 3 days before its completion. In how many days, in all, was the work completed ?

P alone can complete a work in 16 days and Q alone can complete the same work in 20 days. P and Q start the work together but Q leaves the work 7 days before the completion of work. In how many days the total work will be completed

F alone can complete a work in 24 days and G alone can complete the same work in 32 days. F and G start the work together but G leaves the work 8 days before the completion of work. In how many days the total work will be completed?

A,B and C can complete a work in 10,12 and 15 days respectively.They started the work together.But A left the work 5 days before its completion.B also left the work 2 days after A left.In how many days was the work completed? 4 b.15 c.7 d.8

A, B and C can complete a piec of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work in completed ?