Both X and Y together can complete a wor...

Both X and Y together can complete a work in 12 days and Y alone can complete the same work in 30 days. In how many days will X alone complete the work?

A

15

B

20

C

18

D

16

Text Solution

AI Generated Solution

To solve the problem step by step, we can follow these instructions: ### Step 1: Determine the total work done by X and Y together. Given that X and Y together can complete the work in 12 days, we can express the total work in terms of units. If we assume the total work is 60 units (as derived from the LCM calculation), then: \[ \text{Work done by X and Y in 1 day} = \frac{60 \text{ units}}{12 \text{ days}} = 5 \text{ units/day} \] ...
Promotional Banner

Similar Questions

Explore conceptually related problems

X, Y and Z together can complete a work in 20 days. Y and Z can complete the same work in 30 days. In how many days X alone can complete the same work?

A alone can complete a work in 12 days and B alone can complete the same work in 24 days. In how many days can A and B together complete the same work?

C alone can complete a work in 20 days and D alone can complete the same workin 30 days. In how many days C and D together can complete the same work?

A and B together can complete a piece of work in 4 days. If A alone can complete the same work in 12 days, in how many days can B alone complete that work ?

P and Q together can complete a work in 20 days. If P alone can complete the same work in 36 days, then in how many days Q alone can complete the same work?

Mukesh and Dinesh together can complete a work in 120 days. Mukesh alone can complete the work in 150 days. In how many days can Dinesh alone complete the work?

A and B together can complete a work in 35 days while A alone can complete the same work in 60 days. In how many days, B alone will be able to complete the same work?