Smith and Ajit can complete a task in 12 days and 18 days respectively. If they work together on a task for 4 days, then the fraction of task that will be left is:

A

`""_(9)^(4)`

B

`""_(9)^(1)`

C

`""_(9)^(2)`

D

`""_(9)^(5)`

Text Solution

Verified by Experts

The correct Answer is:
A
Promotional Banner

Similar Questions

Explore conceptually related problems

A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is :

A can do a work in 15 days and B in 20 days. If they together work on it for 4 days, then the fraction of the work that is left is :

A alone can do a task in 35 days and B alone in 14 days. If they work on it together for 4 days, then what fraction of the task is left?

Two persons A and B can complete a task in 10 days and 15 days, respectively. They work together and A leaves 5 days before the task is completed After that, B alone completes the remaining task The number of days taken to complete the whole task is :

A alone can complete a task in 3 days. B alone can complete the same task in 7 days If A and B work together for 2 days, what fraction of the task will be left?