21 workers can repair a road in 40 days....

21 workers can repair a road in 40 days. If they are joined by 7 more workers, then in how much time (in days) the road can be repaired?

A

27

B

28

C

30

D

32

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we can follow these calculations: ### Step 1: Calculate the total work done by the initial workers We know that 21 workers can repair a road in 40 days. We can calculate the total work done in terms of worker-days. \[ \text{Total Work} = \text{Number of Workers} \times \text{Days} = 21 \text{ workers} \times 40 \text{ days} = 840 \text{ worker-days} \] **Hint:** To find total work, multiply the number of workers by the number of days they work. ### Step 2: Determine the new total number of workers After 7 more workers join, the total number of workers becomes: \[ \text{Total Workers} = 21 + 7 = 28 \text{ workers} \] **Hint:** Simply add the new workers to the existing number of workers to find the total. ### Step 3: Calculate the time taken to complete the work with the new number of workers Now, we need to find out how many days it will take for 28 workers to complete the same amount of work (840 worker-days). We use the formula: \[ \text{Days} = \frac{\text{Total Work}}{\text{Number of Workers}} = \frac{840 \text{ worker-days}}{28 \text{ workers}} \] Calculating this gives: \[ \text{Days} = \frac{840}{28} = 30 \text{ days} \] **Hint:** To find the number of days, divide the total work by the number of workers. ### Conclusion Thus, if 21 workers are joined by 7 more workers, the road can be repaired in **30 days**. **Final Answer:** 30 days
Promotional Banner

Similar Questions

Explore conceptually related problems

40 persons can repair a bridge in 12 days. If 8 more persons join them, then in how many days bridge can be repaired?

If 15 workers can earn ₹1,800 in 10 days. Find the earning (in ₹) of 5 workers in 8 days.

A group of workers can complete a job in 120 days. If there were 4 more such workers then the work could be finished in 12 days less what was the actual strength of workers?

14 workers can build a wall in 42 days. One worker can build it in

If 8 men can do a piece of work in 14 days, then in how much time (in days) will 7 men do the same piece of work?