X and Y understock to do a piece of work...

X and Y understock to do a piece of work for Rs 5400. X alone could do this work in 18 days and Y alone could do this work in 24 dys. With the assistance of Z they finished the work in 8 days. What is the share (in Rs) of Z?

A

1200

B

1500

C

1600

D

1800

Text Solution

Verified by Experts

The correct Answer is:
A