Robin can do a work alone in 9 days. Ami...

Robin can do a work alone in 9 days. Amit can do the same work alone in 6 days. Both of them finish the work together and they get a total Rs 2500. What is the share (in Rs) of Robin?

A

1700

B

1200

C

1500

D

1000

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem, we need to determine the share of Robin from the total payment of Rs. 2500 based on the amount of work he and Amit can do. ### Step-by-Step Solution: 1. **Calculate Robin's Work Rate:** Robin can complete the work alone in 9 days. Therefore, his work rate (amount of work done in one day) is: \[ \text{Robin's 1 day's work} = \frac{1}{9} \] 2. **Calculate Amit's Work Rate:** Amit can complete the work alone in 6 days. Therefore, his work rate is: \[ \text{Amit's 1 day's work} = \frac{1}{6} \] 3. **Calculate Combined Work Rate:** When Robin and Amit work together, their combined work rate is the sum of their individual work rates: \[ \text{Combined work rate} = \frac{1}{9} + \frac{1}{6} \] To add these fractions, we need a common denominator. The least common multiple of 9 and 6 is 18. \[ \frac{1}{9} = \frac{2}{18}, \quad \frac{1}{6} = \frac{3}{18} \] Therefore, \[ \text{Combined work rate} = \frac{2}{18} + \frac{3}{18} = \frac{5}{18} \] 4. **Determine the Ratio of Work Done:** The ratio of work done by Robin and Amit can be calculated using their individual work rates: \[ \text{Ratio of Robin's work to Amit's work} = \frac{\frac{1}{9}}{\frac{1}{6}} = \frac{6}{9} = \frac{2}{3} \] This means for every 2 parts of work Robin does, Amit does 3 parts. 5. **Calculate Total Parts of Work:** The total parts of work done is: \[ 2 + 3 = 5 \text{ parts} \] 6. **Calculate Robin's Share of Payment:** Since the total payment is Rs. 2500, Robin's share can be calculated based on the ratio of work done: \[ \text{Robin's share} = \frac{2}{5} \times 2500 = 1000 \] ### Final Answer: Robin's share of the payment is Rs. 1000. ---

To solve the problem, we need to determine the share of Robin from the total payment of Rs. 2500 based on the amount of work he and Amit can do. ### Step-by-Step Solution: 1. **Calculate Robin's Work Rate:** Robin can complete the work alone in 9 days. Therefore, his work rate (amount of work done in one day) is: \[ \text{Robin's 1 day's work} = \frac{1}{9} ...
Promotional Banner

Similar Questions

Explore conceptually related problems

Kim can do a work in 3days while David can do the same work in 2 days.Both of them finish the work together and get Rs.150. What is the share of Kim ? Rs.30 b.Rs.60 c.Rs.70 d.Rs.75

A can do a work in 8 days , B can do the same work in 10 days and C can do the same work in 12 days . If all three of them do the same work together and they are paid Rs. 7400, what is the share (in Rs.) of B ?

S can finish 50% of a work in a day. T can do 25% of the work in a day. Both of them together will finish the work in...days.