X and Y together can finish a job in 6 d...

X and Y together can finish a job in 6 days. X can alone do the same job in 12 days. How long will Y alone take to do the same job ?

A

16 days

B

12 days

C

10 days

D

8 days

Text Solution

AI Generated Solution

Promotional Banner

Similar Questions

Explore conceptually related problems

A and B working together can do 30% of the work in 6 days. B alone can do the same work in 25 days. How long will A alone take to complete the same work?

A and B together can do a job in 15 days and A alone could do the same job in 20 days how many days would B take to do half the job if he worked alone

Rohan and Rohit together can do a certain job in 10 days while Rohan alone can do the same job in 15 days. How many days Rohit alone will do the same job ?

Rohan and Rohit together can do a certain job in 10 days while Rohan alone can do the same job in 15 days. How many days Rohit alone will do the same job? (a)25 days (b)32 days (c)35 days (d)30 days

X and Y together can finish a task in 12 days. If Y alone can finish the same task in 15 days, then how many days will X alone take to finish the task ?

A and B together can do a piece of work in 12 days and A alone can complete the work in 18 days. How long will B alone take to complete the job ?

A and B together can do a piece of work in 12 days and A alone can complete the work in 18 days. How long will B alone take to complete the job ?

A and B working together can do a piece of work in 12 days and A alone can caomplete the work in 18 days. How long will B alone take to complete the job?