Home
Class 14
MATHS
Manish is four times as efficient as Pun...

Manish is four times as efficient as Puneet. Manish takes 90 days less than Puneet to complete a book. If both of them work together, then in how many days the book will be completed?

A

28

B

25

C

24

D

30

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we can follow these steps: ### Step 1: Define the efficiencies Let Puneet's efficiency be \( E \). Since Manish is four times as efficient as Puneet, Manish's efficiency will be \( 4E \). ### Step 2: Define the time taken to complete the book Let Puneet take \( D \) days to complete the book. Therefore, Manish will take \( D - 90 \) days to complete the same book. ### Step 3: Relate efficiency to time The relationship between efficiency and time is given by: \[ \text{Efficiency} = \frac{\text{Total Work}}{\text{Time Taken}} \] Since both are completing the same work (let's assume the total work is 1 book), we can express their efficiencies in terms of days: - For Puneet: \[ E = \frac{1}{D} \] - For Manish: \[ 4E = \frac{1}{D - 90} \] ### Step 4: Set up the equation From the efficiencies, we can set up the equation: \[ 4 \left(\frac{1}{D}\right) = \frac{1}{D - 90} \] Multiplying both sides by \( D(D - 90) \) to eliminate the denominators gives: \[ 4(D - 90) = D \] ### Step 5: Solve for \( D \) Expanding the equation: \[ 4D - 360 = D \] Rearranging gives: \[ 4D - D = 360 \] \[ 3D = 360 \] \[ D = 120 \] ### Step 6: Calculate Manish's time Now that we have \( D \), we can find the time taken by Manish: \[ \text{Time taken by Manish} = D - 90 = 120 - 90 = 30 \text{ days} \] ### Step 7: Calculate the combined work rate Now, we can find their combined work rate. - Manish's work rate is \( \frac{1}{30} \) (books per day). - Puneet's work rate is \( \frac{1}{120} \) (books per day). The combined work rate when both work together is: \[ \text{Combined Work Rate} = \frac{1}{30} + \frac{1}{120} \] To add these fractions, we need a common denominator, which is 120: \[ \frac{1}{30} = \frac{4}{120} \] Thus, \[ \text{Combined Work Rate} = \frac{4}{120} + \frac{1}{120} = \frac{5}{120} = \frac{1}{24} \] ### Step 8: Calculate the time taken when working together If their combined work rate is \( \frac{1}{24} \), it means together they can complete the book in: \[ \text{Time} = \frac{1 \text{ book}}{\frac{1}{24} \text{ books per day}} = 24 \text{ days} \] ### Final Answer Thus, the book will be completed in **24 days** when both Manish and Puneet work together. ---
Promotional Banner

Similar Questions

Explore conceptually related problems

A is 1.5 times efficient than B therefore takes 8 days less than B to complete a work. If A and B work on alternate days and A works on first day, then in how many days the work will be completed?

A is 40 % more efficient than B and B is 20 % less efficient than C. If A takes 6 days less than C to complete a work, then in how many days will B complete this work ?

P is twice as efficient as 0.Q takes 12 days to complete a job. If both of them work together, how much time will they take to complete the job? (A) 6 days (B) 4 days (C) 5 days (D) 3 days

X works four times as fast as Y.Y takes 60 days more than X to complete a job. Find the time in which X and Y working together can complete the job ( in days)