If 40 workers can complete a task in 24 days, then, find the time taken by 16 workers to complete twice the work.

A

125 days

B

122 days

C

120 days

D

116 days

Text Solution

Verified by Experts

The correct Answer is:
C
Promotional Banner

Similar Questions

Explore conceptually related problems

If 40 men can complete a job in 6 days, then find the number fo days taken by 60 men to complete it.

Rahul takes twice as such time as Manick and thrice as much time a Sachin a job.If working together,they can complete the job in 4 days, find the time taken by each of them separately to complete the work.

Type 1 workers are two-and-a-half times as efficient as Type 2 workers. If 12 Type 1 workers can complete a task in 10 days. How many days would it take 6 Type 1 and 10 Type 2 workers to complete the same task.

Shailendra, Amit and Suraj can complete a work in 6, 12 and 15 days respectively. Find the time taken to complete the work if they are working together.

Type 1 workers can do three times the work of Type 2 workers. Twelve Type 1 workers can complete a task in 10 days. How many days would it have taken 4 Type 1 and 8 Type 2 workers to complete the same task?

A takes twice the time taken by B and thrice the time taken by C to do a particular piece of work. Working together, they can complete the work in 2 days. Find the number of days taken by A, B and C respectively to complete the work alone