24 men can repair a road in 50 days. If ...

24 men can repair a road in 50 days. If they are joined by 16 more men, then in how much time (in days) the road can be repaired?

A

28

B

25

C

32

D

30

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we can follow these calculations: ### Step 1: Calculate the total work done in man-days We know that 24 men can repair the road in 50 days. Therefore, the total work can be calculated in terms of man-days. \[ \text{Total Work} = \text{Number of Men} \times \text{Number of Days} = 24 \text{ men} \times 50 \text{ days} = 1200 \text{ man-days} \] ### Step 2: Determine the total number of men after adding more workers Initially, there are 24 men. If 16 more men join, the total number of men becomes: \[ \text{Total Number of Men} = 24 + 16 = 40 \text{ men} \] ### Step 3: Calculate the number of days required for 40 men to complete the same work Now, we need to find out how many days it will take for 40 men to complete the same amount of work (1200 man-days). Let \( D \) be the number of days required for 40 men to complete the work. The equation for the total work in man-days can be set up as follows: \[ \text{Total Work} = \text{Number of Men} \times \text{Number of Days} \] \[ 1200 \text{ man-days} = 40 \text{ men} \times D \text{ days} \] ### Step 4: Solve for \( D \) Rearranging the equation to solve for \( D \): \[ D = \frac{1200 \text{ man-days}}{40 \text{ men}} = 30 \text{ days} \] ### Conclusion Thus, if 16 more men join the original 24 men, the road can be repaired in **30 days**. ---
Promotional Banner

Similar Questions

Explore conceptually related problems

40 persons can repair a bridge in 12 days. If 8 more persons join them, then in how many days bridge can be repaired?

35 men can reap a field in 8 days. In how many days can 20 men reap it?

A constrator employed 210 men to build a house in 60 days. After 12 days.he was joined by 70 more men. In how many days will the remaining work be finished? Hint. 210 men can complete the remaning work in 48 days.Find in how many days 280 men can do it.

A certain number of men can do a work in 60 days. If there were 8 men less it could be finished in 10 days more. How many men are there?

A certain number of men can do a work in 60 days. If there were 8 men more it could be finished in 10 days less. How many men are there?

18 men can earn Rs. 360 in 5 days . How much money will 15 men earn in 9 days ?