P can make a table in 16 days while Q ca...

P can make a table in 16 days while Q can make it in 20 days. Q started the work and did that work for 5 days. In how many days P can complete the remaining work?

A

10

B

12

C

15

D

18

Text Solution

Verified by Experts

The correct Answer is:
B
Promotional Banner

Similar Questions

Explore conceptually related problems

P can do a piece of work in 25 days and Q can do the same work in 15 days. In how many days they can complete the work by working together?

Malini can do a piece of work in 20 days, while Shalini can do it in 25 days. Shalini started the work and after 5 days Malini joined her.They together completed the remaining work. How ,many days did they take to complete the whole work?

Malini can do a piece of work in 20 days, while Shalini can do it in 25 days. Shalini started the work and after 5 days Malini joined her.They together completed the remaining work. How ,many days did they take to complete the whole work?

A and B can do a piece of work in 12 days and B and C can do the same piece of work in 16 days.A work for 5 days and B work for 7 days and C complete the remaining work in 13 days then in how many days C would complete the same work?

A is twice as fast as B and together they can complete a work in 20 days. In how many days can A alone complete the work?