A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done `(2)/(3)` of the work. How many men can be discharge now so that the work may finish in time?

A

40

B

50

C

48

D

56

Text Solution

Verified by Experts

The correct Answer is:
D

64 दिनों में पूण किया गया काम = `2/3`
माना प्रत्येक आदमी की क्षमता x है। `therefore` 120x `xx` 64 = `2/3`
`therefore x = 2/(3 xx120 xx 64 ) = (1/(3 xx 120 xx 32))`
शेष दिन = 124-64 = 60
शेष दिन = 1-`2/3` = `(1/3)`
माना y आदमी को हटाया गया `therefore (120 -y ) xx(1)/(3 xx 120 xx 32))xx 60 = 1/3`
120 y = 120 -64 = 56 दिन
Promotional Banner

Similar Questions

Explore conceptually related problems

A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that they had already done 2/3 of the work. How many men can be discharged now so that the work inay finish in time?

A contractor undertakes to make a mall in 60 days and he employs 30 men. After 30 days it is found that only one- third of the work is completed. How many extre men should he employ so that the work is completed on time?

A man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. How many additional men should he employ so that the whole work is finished in time ?

A contractor undertakes to complete a road 360 m long in 120 days and employs 30 men for the work. After 60 days he finds that only 120 m length of the road has been made. How many more men should he employ so that the work may be completed in time ?

A contractor undertook to complete the work in 40 days and he deployed 20 men for his work. 8 days before the scheduled time he realised that (1)/(3)rd of the work was still to be done. How many more men were required to complete the work in stipulated time?

90 men are engaged to do a piece of work in 40 days but it is found that in 25 days, 2/3 work is completed. How many men should be allowed to go off, so that the work may be finished in time?

A man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. The number of additional men that should be appointed so that the whole work will be finished in time is: (A) 50 (B) 75 (C) 100 (D) 150