Home
Class 14
MATHS
A and B can do a work in 15 days and 10 ...

A and B can do a work in 15 days and 10 days respectively. They started working together but after 2 days for some reason B had to leave the work and A alone did the remaining work. In how many days total work was finished?
A तथा B किसी कार्य को पूरा करने में क्रमशः 15 दिन तथा 10 दिन का समय लेते है। उन्होनें मिलकर कार्य करना आरंभ किया किंतु 2 दिन पश्चात किसी कारणवश B को कार्य छोड़ना पड़ा तथा शेष कार्य अकेले A ने पूरा किया। संपूर्ण कार्य कितने समय में पूरा हुआ?

A

10 days/10 दिन

B

8 days/8 दिन

C

12 days/12 दिन

D

15 days/15 दिन

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem, we need to determine how long it takes for A and B to complete the work together and then how long A takes to finish the remaining work after B leaves. ### Step-by-step Solution: 1. **Determine the work rates of A and B:** - A can complete the work in 15 days. Therefore, A's work rate is \( \frac{1}{15} \) of the work per day. - B can complete the work in 10 days. Therefore, B's work rate is \( \frac{1}{10} \) of the work per day. 2. **Calculate the combined work rate of A and B:** - Combined work rate of A and B = A's work rate + B's work rate \[ \text{Combined work rate} = \frac{1}{15} + \frac{1}{10} \] - To add these fractions, we need a common denominator. The least common multiple of 15 and 10 is 30. \[ \frac{1}{15} = \frac{2}{30}, \quad \frac{1}{10} = \frac{3}{30} \] - Therefore, \[ \text{Combined work rate} = \frac{2}{30} + \frac{3}{30} = \frac{5}{30} = \frac{1}{6} \] - This means together, A and B can complete \( \frac{1}{6} \) of the work in one day. 3. **Calculate the work done in the first 2 days:** - In 2 days, the amount of work completed by A and B together is: \[ \text{Work done in 2 days} = 2 \times \frac{1}{6} = \frac{2}{6} = \frac{1}{3} \] 4. **Determine the remaining work:** - Since \( \frac{1}{3} \) of the work is done, the remaining work is: \[ \text{Remaining work} = 1 - \frac{1}{3} = \frac{2}{3} \] 5. **Calculate how long it takes A to finish the remaining work:** - A's work rate is \( \frac{1}{15} \) of the work per day. To find out how many days A needs to complete \( \frac{2}{3} \) of the work: \[ \text{Days required by A} = \frac{\text{Remaining work}}{\text{A's work rate}} = \frac{\frac{2}{3}}{\frac{1}{15}} = \frac{2}{3} \times 15 = 10 \text{ days} \] 6. **Calculate the total time taken to complete the work:** - Total time = Time worked together + Time taken by A alone \[ \text{Total time} = 2 \text{ days} + 10 \text{ days} = 12 \text{ days} \] ### Final Answer: The total work was finished in **12 days**.

To solve the problem, we need to determine how long it takes for A and B to complete the work together and then how long A takes to finish the remaining work after B leaves. ### Step-by-step Solution: 1. **Determine the work rates of A and B:** - A can complete the work in 15 days. Therefore, A's work rate is \( \frac{1}{15} \) of the work per day. - B can complete the work in 10 days. Therefore, B's work rate is \( \frac{1}{10} \) of the work per day. ...
Promotional Banner