Home
Class 14
MATHS
A and B can do a work in 8 days, B and C...

A and B can do a work in 8 days, B and C can do the same work in 12 days. A, B and C together can finish it in 6 days. A and C together will do it in:
A और B मिलकर किसी काम को 8 दिन में पूरा कर सकते हैं। B और C उसी काम को 12 दिन में कर सकते हैं। A, B और C मिलकर उसी काम को 6 दिन में पूरा कर सकते हैं। बताइये कि A और C मिलकर उसी काम को कितने दिन में समाप्त करेंगे ?

A

4 days / दिन

B

6 days / दिन

C

8 days / दिन

D

12 days/दिन

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem, we will first determine the efficiencies of A, B, and C based on the information given. 1. **Determine the total work done**: We can assume the total work is represented by the least common multiple (LCM) of the days taken by A and B, B and C, and A, B, and C. - A and B can complete the work in 8 days, so their combined efficiency is \( \frac{1}{8} \) of the work per day. - B and C can complete the work in 12 days, so their combined efficiency is \( \frac{1}{12} \) of the work per day. - A, B, and C together can complete the work in 6 days, so their combined efficiency is \( \frac{1}{6} \) of the work per day. The LCM of 8, 12, and 6 is 24. Therefore, we can assume the total work is 24 units. 2. **Calculate the efficiencies**: - Let the efficiency of A be \( a \), B be \( b \), and C be \( c \). - From A and B: \[ a + b = \frac{24}{8} = 3 \quad \text{(Equation 1)} \] - From B and C: \[ b + c = \frac{24}{12} = 2 \quad \text{(Equation 2)} \] - From A, B, and C: \[ a + b + c = \frac{24}{6} = 4 \quad \text{(Equation 3)} \] 3. **Solve the equations**: - From Equation 1: \( a + b = 3 \) - From Equation 2: \( b + c = 2 \) - From Equation 3: \( a + b + c = 4 \) We can add Equations 1 and 2: \[ (a + b) + (b + c) = 3 + 2 \] \[ a + 2b + c = 5 \quad \text{(Equation 4)} \] Now we can subtract Equation 3 from Equation 4: \[ (a + 2b + c) - (a + b + c) = 5 - 4 \] \[ 2b - b = 1 \] \[ b = 1 \] 4. **Substitute back to find A and C**: - Substitute \( b = 1 \) into Equation 1: \[ a + 1 = 3 \] \[ a = 2 \] - Substitute \( b = 1 \) into Equation 2: \[ 1 + c = 2 \] \[ c = 1 \] 5. **Find the efficiency of A and C together**: - The efficiency of A and C together: \[ a + c = 2 + 1 = 3 \] 6. **Calculate the time taken by A and C to finish the work**: - Time taken = Total Work / Efficiency \[ \text{Time} = \frac{24}{3} = 8 \text{ days} \] Thus, A and C together will complete the work in **8 days**.

To solve the problem, we will first determine the efficiencies of A, B, and C based on the information given. 1. **Determine the total work done**: We can assume the total work is represented by the least common multiple (LCM) of the days taken by A and B, B and C, and A, B, and C. - A and B can complete the work in 8 days, so their combined efficiency is \( \frac{1}{8} \) of the work per day. - B and C can complete the work in 12 days, so their combined efficiency is \( \frac{1}{12} \) of the work per day. - A, B, and C together can complete the work in 6 days, so their combined efficiency is \( \frac{1}{6} \) of the work per day. ...
Promotional Banner