If 30 men can do a job in 30 days, find ...

If 30 men can do a job in 30 days, find what part of the job can be completed by 1 man in 1 day.

A

`1/30`

B

`1/900`

C

`1/90`

D

`1/60`

Text Solution

Verified by Experts

The correct Answer is:
B