Home
Class 14
MATHS
A and B can complete a task in 40 days a...

A and B can complete a task in 40 days and 16 days respectively. A started the task alone and then after 12 days B joined him till the completion of the task. How long did the task last after B joined the task?

A

8 days

B

6 days

C

14 days

D

12 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will follow these calculations: ### Step 1: Determine the work rates of A and B - A can complete the task in 40 days, so A's work rate is: \[ \text{Work rate of A} = \frac{1 \text{ task}}{40 \text{ days}} = \frac{1}{40} \text{ tasks per day} \] - B can complete the task in 16 days, so B's work rate is: \[ \text{Work rate of B} = \frac{1 \text{ task}}{16 \text{ days}} = \frac{1}{16} \text{ tasks per day} \] ### Step 2: Calculate the total work in terms of units - To find a common unit for the work, we can use the least common multiple (LCM) of 40 and 16. The LCM of 40 and 16 is 80. Therefore, we can consider the total work to be 80 units. ### Step 3: Calculate the work done by A in the first 12 days - In 12 days, A will complete: \[ \text{Work done by A in 12 days} = 12 \times \frac{1}{40} = \frac{12}{40} = \frac{3}{10} \text{ of the task} \] - In terms of units, this is: \[ \text{Units completed by A} = 12 \times 2 = 24 \text{ units} \] ### Step 4: Calculate the remaining work after A's initial 12 days - The total work is 80 units, and A has completed 24 units. Therefore, the remaining work is: \[ \text{Remaining work} = 80 - 24 = 56 \text{ units} \] ### Step 5: Calculate the combined work rate of A and B - When B joins A, their combined work rate is: \[ \text{Combined work rate} = \frac{1}{40} + \frac{1}{16} \] - To add these fractions, we find a common denominator (which is 80): \[ \frac{1}{40} = \frac{2}{80}, \quad \frac{1}{16} = \frac{5}{80} \] - Therefore, \[ \text{Combined work rate} = \frac{2}{80} + \frac{5}{80} = \frac{7}{80} \text{ tasks per day} \] ### Step 6: Calculate the time taken to complete the remaining work - To find the time taken to complete the remaining 56 units of work at the combined rate of \(\frac{7}{80}\) tasks per day, we set up the equation: \[ \text{Time} = \frac{\text{Remaining work}}{\text{Combined work rate}} = \frac{56}{\frac{7}{80}} = 56 \times \frac{80}{7} = \frac{4480}{7} \approx 640 \text{ days} \] ### Step 7: Final Calculation - The exact time in days is: \[ \text{Time} = 640 \div 7 \approx 91.43 \text{ days} \] ### Conclusion The task lasted approximately **91.43 days** after B joined. ---
Promotional Banner

Similar Questions

Explore conceptually related problems

A and B can do a piece of work in 20 days and 12 days respectively. A started the work alone and then after 4 days B joined him till the completion of the work. How long did the work last?

Two persons A and B can complete a task in 10 days and 15 days, respectively. They work together and A leaves 5 days before the task is completed After that, B alone completes the remaining task The number of days taken to complete the whole task is :

Ravi can complete a task in 6 days and Mohan can complete the same task in 9 days. In how many days can Ravi and Mohan together complete the same task?

A, b and C can alone complete a work in 10, 12 and 15 days respectively. A and C started the work and after working for 4 days, A left and B joined. In how many days the total work was completed ?