X, Y and Z can complete a piece of work ...

X, Y and Z can complete a piece of work in 8, 20 and 25 days respectively. Working together, they will complete the same work in:

A

`(180)/(43)` days

B

`(162)/(43)` days

C

`(200)/(43)` days

D

`(172)/(43)` days

Text Solution

Verified by Experts

The correct Answer is:
C