Home
Class 14
MATHS
A can complete 33(1)/(3)% of a work in 5...

A can complete `33(1)/(3)`% of a work in 5 days and B can complete 40% of the same work in 10 days. They work together for 5 days and then B left the work. A alone will complete the remaining work in:

A

`7(1)/(2)` days

B

5 days

C

7 days

D

`5(1)/(2)` days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, let's break it down: ### Step 1: Determine the total work A can complete \(33 \frac{1}{3}\%\) of the work in 5 days. First, convert \(33 \frac{1}{3}\%\) to a fraction: \[ 33 \frac{1}{3}\% = \frac{100}{3}\% \] This means A completes \(\frac{100}{3} \div 100 = \frac{1}{3}\) of the work in 5 days. To find the total work, we can set up the equation: \[ \text{Total Work} = 5 \text{ days} \times 3 = 15 \text{ days} \] Thus, the total work can be considered as 15 units. ### Step 2: Determine B's work rate B can complete \(40\%\) of the work in 10 days. Convert \(40\%\) to a fraction: \[ 40\% = \frac{40}{100} = \frac{2}{5} \] This means B completes \(\frac{2}{5}\) of the work in 10 days. To find the total work, we can set up the equation: \[ \text{Total Work} = 10 \text{ days} \times \frac{5}{2} = 25 \text{ days} \] Thus, the total work can be considered as 25 units. ### Step 3: Find the LCM of work rates Now, we need to find the least common multiple (LCM) of the days taken by A and B to complete the work: - A takes 15 days to complete the work. - B takes 25 days to complete the work. The LCM of 15 and 25 is 75 days. ### Step 4: Calculate work done by A and B in one day Now, let's find the work done by A and B in one day: - A's work rate = \(\frac{1}{15}\) of the work per day. - B's work rate = \(\frac{1}{25}\) of the work per day. ### Step 5: Work done by A and B together in one day The combined work done by A and B in one day: \[ \text{Work done by A + Work done by B} = \frac{1}{15} + \frac{1}{25} \] To add these fractions, find a common denominator (which is 75): \[ \frac{1}{15} = \frac{5}{75}, \quad \frac{1}{25} = \frac{3}{75} \] Thus, \[ \text{Combined work} = \frac{5}{75} + \frac{3}{75} = \frac{8}{75} \] ### Step 6: Work done in 5 days In 5 days, the total work done by A and B together: \[ \text{Total work in 5 days} = 5 \times \frac{8}{75} = \frac{40}{75} = \frac{8}{15} \] ### Step 7: Remaining work Now, we need to find the remaining work after 5 days: \[ \text{Remaining work} = 1 - \frac{8}{15} = \frac{15 - 8}{15} = \frac{7}{15} \] ### Step 8: Time taken by A to complete remaining work Now, we need to find out how long A will take to complete the remaining work: A's work rate is \(\frac{1}{15}\) of the work per day. To find the time taken to complete \(\frac{7}{15}\) of the work: \[ \text{Time} = \frac{\text{Remaining work}}{\text{A's work rate}} = \frac{\frac{7}{15}}{\frac{1}{15}} = 7 \text{ days} \] ### Final Answer A alone will complete the remaining work in **7 days**. ---
Promotional Banner

Similar Questions

Explore conceptually related problems

A can do (3)/(5)th of a work in 12 days, B can do (1)/(3) rd of that work in 15 days. They worked together for 12 days and then A left the work , B alone will complete the remaining work in?

A can do 2/5 of a work in 12 days while B can do 66^(2/3)% of the same work in 16 days. They work together for 10 days. B alone will complete the remaining work in

A can complete of a work in 8 days. B can complete 3/5 of the same work in 12 days and C can complete 4/9 of the same work in 8 days. A and B worked together for 5 days. How much time(in days) will C alone take to complete the remaining work?

A can do 4/5 of a work in 20 days and B can do 3/4 of the same work in 15 days. They work together for 10 days. C alone completes the remaining work in 1 day. B and C together can complete 3/4 of the same work in:

A and B can complete a piece of work in 15 days and 10 days, respectively . They work together for 4 days and then B leavs. In how many days will A alone complete the remaining work ?