Home
Class 14
MATHS
A certain numner of men agreed to do a w...

A certain numner of men agreed to do a work in 20 days. 5 men did come for work. Others completed the work in 40 days. Find the number of men who had agreed to do the work originally.

A

A) 8

B

B) 10

C

C) 12

D

D) 15

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem, we need to determine the original number of men who agreed to complete the work in 20 days. Let's break it down step by step. ### Step 1: Define Variables Let \( x \) be the original number of men who agreed to do the work. ### Step 2: Calculate Work Done The total work can be expressed in terms of man-days. If \( x \) men can complete the work in 20 days, the total work \( W \) is: \[ W = x \times 20 \] ### Step 3: Determine Remaining Men Since 5 men did not come for work, the number of men who actually worked is: \[ x - 5 \] ### Step 4: Calculate Work Done by Remaining Men These remaining men completed the work in 40 days. Therefore, the work done by these men can be expressed as: \[ W = (x - 5) \times 40 \] ### Step 5: Set Up the Equation Since the total work \( W \) is the same in both scenarios, we can set the two equations equal to each other: \[ x \times 20 = (x - 5) \times 40 \] ### Step 6: Expand and Simplify the Equation Expanding the right side gives: \[ 20x = 40x - 200 \] ### Step 7: Rearrange the Equation Rearranging the equation to isolate \( x \): \[ 20x - 40x = -200 \] \[ -20x = -200 \] \[ 20x = 200 \] ### Step 8: Solve for \( x \) Dividing both sides by 20 gives: \[ x = 10 \] ### Conclusion The original number of men who had agreed to do the work is \( \boxed{10} \). ---
Promotional Banner

Similar Questions

Explore conceptually related problems

20 men can do a work in 35 days. How many men are needed to complete the same work in 25 days.

A group of men decided to do a work in 10 days, but 5 of them become absent. if the rest of the group did the work in 12 days, find the original number of men?

If 5 men do a piece of work in 28 days, then the number of persons required to do the same work in 7 days is

A certain number of men can do a piece of work in 40 days. If there were 45 men more the work could have been finished in 25 days. Find the original number of men employed in the work (A) 70 (B) 85 (C) 65 (D) 75

12 men of 15 women can do a work in 40 days. 8 men and 10 women can do the work in how many days?