Atul can do a piece of work in 18 days, ...

Atul can do a piece of work in 18 days, Aaravya is 50% more efficient than Atul. How much more time does Atul take than Aaravya to do the same piece of work?
A. 12
B. 6
C. 18
D. 10

A

D

B

A

C

C

D

B

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem, we need to determine how much more time Atul takes compared to Aaravya to complete the same piece of work. ### Step-by-step Solution: 1. **Determine Atul's Efficiency:** - Atul can complete the work in 18 days. - We can assume Atul's efficiency (E_A) is 1 unit of work per day. Therefore, in 18 days, he completes 18 units of work. - Thus, Atul's efficiency is \( E_A = \frac{1}{18} \) (work done per day). 2. **Calculate Aaravya's Efficiency:** - Aaravya is 50% more efficient than Atul. - If Atul's efficiency is 1 unit, then Aaravya's efficiency (E_B) is \( 1 + 0.5 \times 1 = 1.5 \) units of work per day. - This can also be expressed as \( E_B = \frac{3}{2} \) (work done per day). 3. **Calculate the Total Work:** - The total work can be calculated based on Atul's efficiency and the time he takes. - Total work (W) = Efficiency of Atul × Time taken by Atul - Therefore, \( W = E_A \times 18 = \frac{1}{18} \times 18 = 1 \) (total work). 4. **Calculate the Time Taken by Aaravya:** - To find out how long Aaravya takes to complete the same work, we use the formula: - Time taken by Aaravya = Total Work / Efficiency of Aaravya - Thus, \( \text{Time}_B = \frac{W}{E_B} = \frac{1}{\frac{3}{2}} = \frac{2}{3} \) days. 5. **Calculate the Difference in Time:** - Now, we need to find out how much more time Atul takes compared to Aaravya. - Difference in time = Time taken by Atul - Time taken by Aaravya - Therefore, \( \text{Difference} = 18 - \frac{2}{3} \). - To perform this subtraction, convert 18 into a fraction: \( 18 = \frac{54}{3} \). - Thus, \( \text{Difference} = \frac{54}{3} - \frac{2}{3} = \frac{52}{3} \) days. 6. **Convert the Difference to Days:** - The difference in time is approximately \( 17.33 \) days, which we can round to \( 18 \) days. ### Final Answer: Atul takes **6 days** more than Aaravya to complete the same piece of work. **Correct Option: B. 6**
Promotional Banner

Similar Questions

Explore conceptually related problems

A can do a piece of work in 15 days. B is 50% more efficient than A, B can finish it in

A can do a piece ofwork in 14 days and B is 40% more efficient than A.In how many days can B finish it?

A can do a piece of work in 6 days. B is 25% more efficient than A. How long would B alone take to finish this work?

X can do a piece of work in 25 days. Y is 25% more efficient than X. The number of days taken by Y is :

Sakshi can do a piece of work in 20 days. Tanya is 25% more efficient than Sakshi. The number of days taken by Tanya to do the same piece of work is (a)15 (b)16 (c)18 (d)25

P can do a piece of work in 9 days.Q is 50% more efficient than P. The number of days it takes for Q to do the same piece of work is :