B is twice efficient than A and the total time taken to complete the work by both A and B together is 22 days. Find the number of days taken by B to complete the work alone.

A

11 days

B

44 days

C

33 days

D

30 days

Text Solution

Verified by Experts

The correct Answer is:
C
Promotional Banner

Similar Questions

Explore conceptually related problems

A is twice as efficient as B and they together can complete a piece of work in 24 days. Find the number of days, that A alone takes to compelete the work.

A is twice as efficient as B and they together can complete a piece of work in 24 days. Find the number of days, that A alone takes to compelete the work.

A takes twice the time taken by B and thrice the time taken by C to do a particular piece of work. Working together, they can complete the work in 2 days. Find the number of days taken by A, B and C respectively to complete the work alone

If a work can be completed by A in 30 days and by B in 60 days. Then, the number of days taken by them to complete the work, working together is

A takes 6 days less than the time taken by B to finish a piece of work.If both A and B together can finish it in 4 days.Find the time taken by B to finish the work.