P can do a piece of work in 60 days & Q can do the same work in 50 days. Find the ratio of working efficiencies of P to Q.
A `1/3` B. `6/3` C. `5/6` D. `4/5`

A

A

B

B

C

C

D

D

Text Solution

Verified by Experts

The correct Answer is:
C
Promotional Banner

Similar Questions

Explore conceptually related problems

If A can do a piece of work in p days and B can do the same in q days: A and B together can finish it in how many days

A can do a work in x days and B can do the same work in y days. If xgty , then who can do more work in 6 days?

P can do a piece of work in 25 days and Q can do the same work in 15 days. In how many days they can complete the work by working together?

A can do a piece of work in 9 days and B can do the same work in 15 days. If they work together, in what ratio A and B will receive their wages?

A can do a piece of work in 9 days and B can do the same in 12 days. In how days can the work be completed if A and B work together?

P can do a piece of work in 20 days and Q can do the same piece of work in 60 days. They start working together and work for 5 days and then both leave the work. R alone finishes the remaining work in 10 days. In how many days will R alone finish the whole work?