A work can be completed by 35 workers in...

A work can be completed by 35 workers in 30 days. If 5 workers leave after every 10 days then in how many days will the work be completed ?

A

50 days

B

40 days

C

`35.5` days

D

`37.5` days

Text Solution

Verified by Experts

The correct Answer is:
D
Promotional Banner

Similar Questions

Explore conceptually related problems

How many workers are required for completing the construction work in the 10 days ? (i) 20% of the work can be completed by 8 workers in 8 days. (ii) 20 workers can complete the work in 16 days. (iii) One - eighth of the work can ve completed by 8 workers in 5 days.

A and B can do a work in 30 days and 10 days respectively. If they work on alternate days beginning with A, in how many days will the work be completed?

A and B can do a work in 30 days and 10 days respectively. If they work on alternate days beginning with A, in how many days will the work be completed?

Vinay and Varma can do a work in 30 days and 60 days respectively. If they work on alternate days beginning with Vinay, in how many days will the work be completed?

Vinay and Varma can do a work in 30 days and 60 days respectively. If they work on alternate days beginning with Vinay, in how many days will the work be completed?