A contractor takes a contract to complete a road in 60 days and employed 105 labours. After 25 days, he found that one-third work is completed. How many more labours he requires to complete the remaining work in time?

A

75

B

105

C

150

D

45

Text Solution

Verified by Experts

The correct Answer is:
D
Promotional Banner

Similar Questions

Explore conceptually related problems

A contractor takes a contract to complete a road in 60 days and employs 70 labours. After 25 days, he found that one fourth work is completed. How many more labours he requires to complete the remaining work in time? एक ठेकेदार 60 दिनों में एक सड़क को पूरा करने का ठेका लेता है और 70 मजदूरों को इस कार्य में लगाता है। 25 दिनों के बाद,एक चौथाई काम पूरा हो जाता है। शेष काम को दिए गए समय पर पूरा करने के लिए उसे कितने और मजदूरों की आवश्यकता पड़ेगी?

A contractor undertakes to make a mall in 60 days and he employs 30 men. After 30 days it is found that only one- third of the work is completed. How many extre men should he employ so that the work is completed on time?

A contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only one-third of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier?

A contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only onethird of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier?

15. A contractor took a contract to complete a work in 60 days, He employed 50 laborers, after 40 days the work was half done. Now How many more laborers should he increase so that the work is completed on time Go (1) 40 laborers (2) 50 laborers (3) 55 laborers (4) 60 laborers

A contractor undertakes to built a walls in 50 days. He employs 50 peoples for the same. However after 25 days he finds that only 40% of the work is complete. How many more man need to be employed to complete the work in time?

A contractor undertakes to complete a road 360 m long in 120 days and employs 30 men for the work. After 60 days he finds that only 120 m length of the road has been made. How many more men should he employ so that the work may be completed in time ?