Home
Class 14
MATHS
A can do a piece of work in 24 days. If ...

A can do a piece of work in 24 days. If B is 50% more efficient than A, then in how many days can B do the same work?

A

12

B

16

C

18

D

15

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem, we will follow these steps: ### Step 1: Determine A's work rate A can complete the work in 24 days. Therefore, A's work rate is: \[ \text{Work rate of A} = \frac{1 \text{ work}}{24 \text{ days}} = \frac{1}{24} \text{ work per day} \] ### Step 2: Calculate B's efficiency B is 50% more efficient than A. To find B's work rate, we first calculate 50% of A's efficiency: \[ \text{50% of A's work rate} = 0.5 \times \frac{1}{24} = \frac{1}{48} \] Now, we add this to A's work rate to find B's work rate: \[ \text{Work rate of B} = \text{Work rate of A} + \text{50% of A's work rate} = \frac{1}{24} + \frac{1}{48} \] ### Step 3: Find a common denominator To add the fractions, we need a common denominator. The least common multiple of 24 and 48 is 48. We convert \(\frac{1}{24}\) to have a denominator of 48: \[ \frac{1}{24} = \frac{2}{48} \] Now we can add the two fractions: \[ \text{Work rate of B} = \frac{2}{48} + \frac{1}{48} = \frac{3}{48} = \frac{1}{16} \text{ work per day} \] ### Step 4: Calculate the time taken by B to complete the work To find out how many days B takes to complete the work, we take the reciprocal of B's work rate: \[ \text{Days taken by B} = \frac{1 \text{ work}}{\text{Work rate of B}} = \frac{1}{\frac{1}{16}} = 16 \text{ days} \] ### Final Answer B can complete the work in **16 days**. ---
Promotional Banner

Similar Questions

Explore conceptually related problems

A can do a piece of work in 24 days. If B is 60% more efficient than A, then how many days does B require to do the same work?

A can do a piece of work in 15 days. B is 50% more efficient than A, B can finish it in

A can do a piece ofwork in 14 days and B is 40% more efficient than A.In how many days can B finish it?

A can do a piece of work in 24 days. If B is 60% more efficient than A, then the number of days required by B to do the same piece of work is :