X alone can do a work in 10 days. Y alon...

X alone can do a work in 10 days. Y alone can do the same in 15 days. X, Y and Z together can do the same work in 3 days. In how many days can Z alone do the work?

A

6

B

9

C

4

D

10

Text Solution

Verified by Experts

Promotional Banner

Similar Questions

Explore conceptually related problems

W and T together can do a work in 140 days. W alone can do the work in 160 days. In how many days can T alone do the work?

X can do 20% of a work in a day, Y can do 25% of the same work in a day and X, Y and Z together can do 50% of the same work in a day. How many per cent of work can be done by Z in a day?

Aman and Raman together can do a work in 10 days. Aman alone can do the work in 12 days. In how many days Raman alone can do the work?