Home
Class 14
MATHS
If 10 men can complete a piece of work i...

If 10 men can complete a piece of work in 12 days by working 7 hours a day, then in how many days can 14 mendo the same work by working 6 hours a day?

A

A. 16

B

B. 15

C

C. 10

D

D. 12

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we can use the concept of work done, which is represented by the formula: \[ \text{Work} = \text{Men} \times \text{Days} \times \text{Hours} \] ### Step 1: Calculate the total work done by 10 men in 12 days working 7 hours a day. Using the formula: \[ \text{Total Work} = \text{Men} \times \text{Days} \times \text{Hours} \] Substituting the values: \[ \text{Total Work} = 10 \, \text{men} \times 12 \, \text{days} \times 7 \, \text{hours} = 840 \, \text{man-hours} \] ### Step 2: Set up the equation for the new scenario with 14 men working 6 hours a day. Let \( D \) be the number of days required for 14 men to complete the same work while working 6 hours a day. The equation will be: \[ \text{Total Work} = 14 \, \text{men} \times D \, \text{days} \times 6 \, \text{hours} \] ### Step 3: Equate the total work from both scenarios. Since the total work remains the same, we can set the two expressions for total work equal to each other: \[ 840 \, \text{man-hours} = 14 \, \text{men} \times D \, \text{days} \times 6 \, \text{hours} \] ### Step 4: Simplify the equation to find \( D \). First, calculate \( 14 \times 6 \): \[ 14 \times 6 = 84 \] Now we can rewrite the equation: \[ 840 = 84D \] To find \( D \), divide both sides by 84: \[ D = \frac{840}{84} = 10 \] ### Conclusion: The number of days required for 14 men to complete the work by working 6 hours a day is **10 days**. ---
Promotional Banner

Similar Questions

Explore conceptually related problems

If 15 men can complete a work in 16 days by working 8 hours daily, then in how many days will 10 men complete the work by working 12 hours daily?

If 25 men can do a piece of work in 36 days working 10 hours a day, then how many men are required to complete the work working 6 hours a day in 20 days?

If 4 men can reap a field in 5 days working 12 hours a day, in how many days can 10 men reap the same field working 8 hours a day?

If 10 men complete half work in 12 days when they work 8 hours per day, In how many days 18 men complete the full when they work 6 hours/day ?

Working 7 hours a day, 18 persons can complete a certain work in 32 days. In how many days would 14 persons complete the same work, working 8 hours a day ?

Fifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, working 6 hours per day ?

Fifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, working 6 hours per day ?

15 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?