P and Q together can do a work in 12 day...

P and Q together can do a work in 12 days. P alone can do the same work in 18 days. In How many days can Q alone complete two-third part of the same work?

A

21

B

30

C

24

D

36

Text Solution

Verified by Experts

The correct Answer is:
C
Promotional Banner

Similar Questions

Explore conceptually related problems

W and T together can do a work in 140 days. W alone can do the work in 160 days. In how many days can T alone do the work?

Aman and Raman together can do a work in 10 days. Aman alone can do the work in 12 days. In how many days Raman alone can do the work?

A and B together can do a piece of work in 12 days and A alone can do it in 18 days. In how many days canBalone do it?

P and Q together can complete a work in 20 days. If P alone can complete the same work in 36 days, then in how many days Q alone can complete the same work?

A and B together can complete a piece of work in 4 days. If A alone can complete the same work in 12 days, in how many days can B alone complete that work ?

Both X and Y together can complete a work in 12 days and Y alone can complete the same work in 30 days. In how many days will X alone complete the work?