36 persons working 8 hours a day can do ...

36 persons working 8 hours a day can do 3 units of work in 12 days. How many persons are required to do 5 units of that work in 16 days, if they work for 6 hours a day?

A

60

B

55

C

45

D

50

Text Solution

Verified by Experts

The correct Answer is:
A