P alone can complete the work in 5 days,...

P alone can complete the work in 5 days,Q alone can do same work in 6 days and R alone can do the same work in 12 days. They jointly complete the work and earn Rs. 5400. What is the share of R?

A

1000

B

1200

C

1500

D

1800

Text Solution

Verified by Experts

The correct Answer is:
A