35 persons are engaged to complete a wor...

35 persons are engaged to complete a work in 60 days. After 32 days it is observed that only (2/5)th part of the work has been done. The number of persons to be engaged to complete the remaining work in the said period is

A

20

B

35

C

30

D

25

Text Solution

Verified by Experts

The correct Answer is:
D
Promotional Banner

Similar Questions

Explore conceptually related problems

A contractor undertook a work to complete in 60 days. But just after 20 days he observed that only (1)/(5)th of the project work had been completed. To complete the work in time in rest days minimum how many workers he had to increase, if there were initially 75 workers were deployed for the task?

If a person X completes ((1)/(n)) thpart of the work in one day then person X will take n days to complete the work.

If a person X completes a piece of work in n days then work done by person X in one day is ((1)/(n)) part of the work.

If 20 persons can do a piece of work in 7 days then calculate the number of persons required to complete the work in 28 days

If 20 persons can do a piece of work in 7 days, then the number of persons required to complete the work in 28 days:

If 40 persons can do a piece of work in 14 days, then the number of persons required to complete the work in 28 days.