A and B together can complete a piece of...

A and B together can complete a piece of work in 12 days. They worked together for 5 days and then A alone finished the rest of the work in 14 days. A alone can complete the work in

A

24 days

B

22 days

C

20 days

D

18 days

Text Solution

Verified by Experts

The correct Answer is:
A
Promotional Banner

Similar Questions

Explore conceptually related problems

A and B together can do a piece of work in 12 days, while B alone can finish it in 30 days. A alone can finish the work in

A can do a piece of work in 34 days. He worked for 14 days and then left. B completed the remaining work in 30 days. In how many days can B alone complete the work?

A and B together can do a piece of work in 12 days, while B alone can finish it in 30 days. In how many days can A alone finish the work?

A can do (3)/(5)th of a work in 12 days, B can do (1)/(3) rd of that work in 15 days. They worked together for 12 days and then A left the work , B alone will complete the remaining work in?