To do a certain work, the ratio of the efficiencies of X and Y is 5:4. Working together, they can complete the same work in 10 days. Y alone starts the work and leaves after 5 days. The remaining work will be completed by X alone in:
किसी निश्चित कार्य को करने के लिए, X और Y की कार्य क्षमताओं का अनुपात 5: 4 है | एक साथ कार्य करते हुए वे इस कार्य को 10 दिनों में समाप्त कर सकते हैं | Y अकेले कार्य शुरू करता है और 5 दिनों के बाद छोड़ देता है | X अकेले शेष कार्य कितने दिनों में पूरा करेगा ?

A

15 days

B

10 days

C

12 days

D

14 days

Text Solution

Verified by Experts

The correct Answer is:
D
Promotional Banner

Similar Questions

Explore conceptually related problems

To do a certain work, the ratio of the efficiencies of A , B and C is 7 : 5 : 6. Working together, they can complete the same work in 35 days. B and C worked together for 21 days. The remaining work will be completed by A alone in : एक निश्चित कार्य को करने के लिए,A, B और C की कार्य क्षमता का अनुपात 7 : 5: 6 है| एक साथ कार्य करते हुए, वे इसी कार्य को 35 दिनों में पूरा कर सकते हैं | B और C ने 21 दिनों तक कार्य किया | शेष कार्य पूरा करने में A को अकेले कितने दिन लगेंगे ?

To do a certain work, the ratio of the efficiencies of A and B is 7 : 5. Working together, they can complete the same work in 17(1)/(2) days. A alone will complete 60% of the same work in:

The efficiencies of A, B and C are in the ratio 5: 3: 8. Working together they can complete a work in 30 days. A and B worked together for 20 days. The remaining work will be completed by C alone in: