Home
Class 14
MATHS
A can do (1)/(3) of a work in 30 days. B...

A can do `(1)/(3)` of a work in 30 days. B can do `(2)/(5)` of the same work in 24 days. They worked together for 20 days. C completed the remaining work in 8 days. Working together A, B and C will complete the same work in:

A

15 days

B

10 days

C

18 days

D

12 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will first determine the work rates of A, B, and C, and then find out how long it will take for A, B, and C to complete the work together. ### Step 1: Calculate the total work in terms of work units. A can do \( \frac{1}{3} \) of the work in 30 days. Therefore, the total work can be considered as 1 unit of work. If A does \( \frac{1}{3} \) of the work in 30 days, then the total work (W) can be calculated as: \[ W = 3 \times 30 = 90 \text{ days of work} \] ### Step 2: Calculate the work rate of A. A's work rate is: \[ \text{Work rate of A} = \frac{1}{3} \text{ of work} / 30 \text{ days} = \frac{1}{90} \text{ of work per day} \] ### Step 3: Calculate the work rate of B. B can do \( \frac{2}{5} \) of the work in 24 days. Therefore, B's work rate is: \[ \text{Work rate of B} = \frac{2}{5} \text{ of work} / 24 \text{ days} = \frac{2}{120} = \frac{1}{60} \text{ of work per day} \] ### Step 4: Calculate the combined work rate of A and B. The combined work rate of A and B is: \[ \text{Combined work rate of A and B} = \frac{1}{90} + \frac{1}{60} \] To add these fractions, find a common denominator, which is 180: \[ \frac{1}{90} = \frac{2}{180}, \quad \frac{1}{60} = \frac{3}{180} \] Thus, \[ \text{Combined work rate of A and B} = \frac{2}{180} + \frac{3}{180} = \frac{5}{180} = \frac{1}{36} \text{ of work per day} \] ### Step 5: Calculate the work done by A and B in 20 days. In 20 days, A and B together will complete: \[ \text{Work done by A and B in 20 days} = 20 \times \frac{1}{36} = \frac{20}{36} = \frac{5}{9} \text{ of the work} \] ### Step 6: Calculate the remaining work. The remaining work after A and B have worked together for 20 days is: \[ \text{Remaining work} = 1 - \frac{5}{9} = \frac{4}{9} \text{ of the work} \] ### Step 7: Calculate the work rate of C. Let’s assume C can complete the remaining work in 8 days. Therefore, C's work rate is: \[ \text{Work rate of C} = \frac{4}{9} \text{ of work} / 8 \text{ days} = \frac{4}{72} = \frac{1}{18} \text{ of work per day} \] ### Step 8: Calculate the combined work rate of A, B, and C. Now, we can find the combined work rate of A, B, and C: \[ \text{Combined work rate of A, B, and C} = \frac{1}{90} + \frac{1}{60} + \frac{1}{18} \] Finding a common denominator (which is 180): \[ \frac{1}{90} = \frac{2}{180}, \quad \frac{1}{60} = \frac{3}{180}, \quad \frac{1}{18} = \frac{10}{180} \] Thus, \[ \text{Combined work rate of A, B, and C} = \frac{2}{180} + \frac{3}{180} + \frac{10}{180} = \frac{15}{180} = \frac{1}{12} \text{ of work per day} \] ### Step 9: Calculate the time taken by A, B, and C to complete the work together. If A, B, and C work together, they will complete the work in: \[ \text{Time} = \frac{1 \text{ unit of work}}{\frac{1}{12} \text{ of work per day}} = 12 \text{ days} \] ### Final Answer: A, B, and C together will complete the work in **12 days**. ---
Promotional Banner

Similar Questions

Explore conceptually related problems

A can do (2)/(5) of a work in 6 days and B can do (2)/(3) of the same work in 12 days. A and B worked together for 6 days. C alone completed the remaining work in 8 days. A and C, working together, will complete the same work in:

A can do 2/5 of a work in 12 days while B can do 66^(2/3)% of the same work in 16 days. They work together for 10 days. B alone will complete the remaining work in

A can do 4/5 of a work in 20 days and B can do 3/4 of the same work in 15 days. They work together for 10 days. C alone completes the remaining work in 1 day. B and C together can complete 3/4 of the same work in:

A can do (3)/(5)th of a work in 12 days, B can do (1)/(3) rd of that work in 15 days. They worked together for 12 days and then A left the work , B alone will complete the remaining work in?

Surbhi can do a piece of work in 24 days. She completed 3/8 of the work and then left it. Amita complete the remaining work in 10 days. Working together, they will complete 125% of the same work in:

A can do a work in 4 days while B can do that same work in 6 days. If they worked together, then that work would be completed in

A and B can do a piece of work in 12 days and B and C can do the same piece of work in 16 days.A work for 5 days and B work for 7 days and C complete the remaining work in 13 days then in how many days C would complete the same work?

A can complete one-third of a work in 10 days and B can do ""_(5)^(3) th of the same work in 24 days. They worked together for 10 days. The remaining work was completed by C alone in 15 days. In how many days can C alone do ""_(3)^(2) of the same work?

A can do a work in 25 days and B can do the same work in 20 days. They work together for 5 days and then A goes away. In how many days will B finish the work?