Working together A and B can do a job in...

Working together A and B can do a job in 40 days, B and C in 36 days and all three together in 24 days. In how many days can B alone do the job?

A

60

B

90

C

72

D

120

Text Solution

Verified by Experts

The correct Answer is:
B