The ratio of the amount of work done by ...

The ratio of the amount of work done by (x-1) labours in (x+1) days and that done by (x+1) labours in (x+2) days is 5:6. Then the value of x is

A

16

B

15

C

17

D

14

Text Solution

Verified by Experts

The correct Answer is:
A
Promotional Banner

Similar Questions

Explore conceptually related problems

If the ratio of the work done by (x + 2) workers in (x-3) days to the work done by (x + 4) workers in (x-2) days is 3:4, then what is the value of x?

Work done by (x+4) mean in (x+5) days is equal to the work done by (x-5) men in (x+20) days. What is the value of x?

If the work done by (x – 1) men in (x + 1) days and the work done by (x + 2) men in (x – 1) days is in the ratio of 9 : 10, then x is equal to .

If (x^2+1/x^2)=6 then the value of (x-1/x) is

If (x+1/x) =2 then the value of (x^5+1/x^5) is:

50 persons can do a work in 12 days, working 6 h per day. 60 persons can do the same work in 8 days, working x h per days.The value of x is