Home
Class 14
MATHS
A contract is to be completed in 75 days...

A contract is to be completed in 75 days and 187 men are to work 15 hours per day. After 65 days, 3/5 of the work is completed. How many additional men may be employed, so that the work may be completed in time each man now working 17 hours per day?

A

495

B

514

C

528

D

532

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will break down the information given and calculate the required values. ### Step 1: Understand the total work and the initial conditions - Total days to complete the work = 75 days - Number of men initially employed = 187 men - Hours worked per day by each man = 15 hours ### Step 2: Calculate the total work in man-hours Total work can be calculated as: \[ \text{Total Work} = \text{Number of Men} \times \text{Hours per Day} \times \text{Total Days} \] \[ \text{Total Work} = 187 \times 15 \times 75 \] Calculating this gives: \[ \text{Total Work} = 187 \times 15 = 2805 \text{ man-hours} \] \[ \text{Total Work} = 2805 \times 75 = 210375 \text{ man-hours} \] ### Step 3: Calculate the work completed in 65 days After 65 days, it is given that \( \frac{3}{5} \) of the work is completed. Therefore, the work done is: \[ \text{Work Done} = \frac{3}{5} \times \text{Total Work} \] Calculating this gives: \[ \text{Work Done} = \frac{3}{5} \times 210375 = 126225 \text{ man-hours} \] ### Step 4: Calculate the remaining work The remaining work to be completed is: \[ \text{Remaining Work} = \text{Total Work} - \text{Work Done} \] Calculating this gives: \[ \text{Remaining Work} = 210375 - 126225 = 84150 \text{ man-hours} \] ### Step 5: Calculate the time left to complete the remaining work The time left to complete the work is: \[ \text{Time Left} = 75 - 65 = 10 \text{ days} \] ### Step 6: Calculate the total man-hours available with the new working hours Each man now works 17 hours per day. Therefore, the total man-hours available with the current workforce (187 men) in the remaining 10 days is: \[ \text{Available Man-Hours} = \text{Number of Men} \times \text{Hours per Day} \times \text{Days Left} \] Calculating this gives: \[ \text{Available Man-Hours} = 187 \times 17 \times 10 = 31790 \text{ man-hours} \] ### Step 7: Calculate the additional man-hours required The additional man-hours required to complete the remaining work is: \[ \text{Additional Man-Hours Required} = \text{Remaining Work} - \text{Available Man-Hours} \] Calculating this gives: \[ \text{Additional Man-Hours Required} = 84150 - 31790 = 52360 \text{ man-hours} \] ### Step 8: Calculate the number of additional men needed Let \( x \) be the number of additional men required. Each man will work 17 hours per day for 10 days, so: \[ x \times 17 \times 10 = 52360 \] \[ x \times 170 = 52360 \] \[ x = \frac{52360}{170} = 308 \] ### Step 9: Calculate the total number of men required The total number of men required is: \[ \text{Total Men} = \text{Initial Men} + \text{Additional Men} = 187 + 308 = 495 \] ### Step 10: Conclusion Thus, the number of additional men that may be employed is: \[ \text{Additional Men} = 308 \]
Promotional Banner