Home
Class 14
MATHS
A and B can complete a task together in ...

A and B can complete a task together in 15 days, while A alone can complete it in 18.75 days. They start working together but A leaves 12.5 days before the completion of the work. For how many days did A and B work together ?

A

10

B

13.75

C

12.5

D

11.25

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we need to determine how many days A and B worked together before A left 12.5 days before the work was completed. ### Step 1: Determine the work done by A and B together. A and B can complete the task together in 15 days. Therefore, the work done by A and B in one day is: \[ \text{Work rate of A and B together} = \frac{1}{15} \text{ of the work per day} \] ### Step 2: Determine the work done by A alone. A can complete the task alone in 18.75 days. Therefore, the work done by A in one day is: \[ \text{Work rate of A} = \frac{1}{18.75} = \frac{4}{75} \text{ of the work per day} \] ### Step 3: Determine the work done by B alone. Let the work done by B in one day be \( b \). Since A and B together can complete the work in 15 days, we have: \[ \frac{1}{15} = \frac{4}{75} + b \] To find \( b \), we first convert \(\frac{1}{15}\) to a fraction with a common denominator: \[ \frac{1}{15} = \frac{5}{75} \] Now substituting: \[ \frac{5}{75} = \frac{4}{75} + b \] Subtracting \(\frac{4}{75}\) from both sides gives: \[ b = \frac{5}{75} - \frac{4}{75} = \frac{1}{75} \text{ of the work per day} \] ### Step 4: Determine the total work. The total work can be considered as 1 unit of work. ### Step 5: Determine how much work is left when A leaves. A leaves 12.5 days before the work is completed. Let \( x \) be the total number of days they worked together. Therefore, the total time to complete the work is \( x + 12.5 \) days. The work done in the last 12.5 days by B alone is: \[ \text{Work done by B in 12.5 days} = 12.5 \times \frac{1}{75} = \frac{12.5}{75} = \frac{1}{6} \text{ of the work} \] ### Step 6: Calculate the work done together. If B completed \(\frac{1}{6}\) of the work alone, then the work done together by A and B is: \[ \text{Work done together} = 1 - \frac{1}{6} = \frac{5}{6} \text{ of the work} \] ### Step 7: Calculate the number of days they worked together. Since A and B together can complete \(\frac{1}{15}\) of the work per day, we can find the number of days they worked together: \[ \text{Days worked together} = \frac{\frac{5}{6}}{\frac{1}{15}} = \frac{5}{6} \times 15 = \frac{75}{6} = 12.5 \text{ days} \] ### Conclusion: A and B worked together for **12.5 days**.
Promotional Banner

Similar Questions

Explore conceptually related problems

A and B can do a piece of work together in 15 days while A alone can do it in 25 days. They start working together but B leaves 5 days before the completion of the work. For how many days did A and B work together?

A can do a work in 12 days and B can do it in 18 days. They started working together. But A leaves 3 days before the work gets over. For how many days did the two work together ?

F alone can complete a work in 24 days and G alone can complete the same work in 32 days. F and G start the work together but G leaves the work 8 days before the completion of work. In how many days the total work will be completed?

P alone can complete a work in 16 days and Q alone can complete the same work in 20 days. P and Q start the work together but Q leaves the work 7 days before the completion of work. In how many days the total work will be completed

A, B and C can complete a piec of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work in completed ?

A can do a piece of work in 10 days while B can do it in 15 days. They begin together but 5 days before the completion of the work, B leaves off. Find the total number of days for the work to be completed .

A can complete a work in 20 days & B can complete the same work in 25 days. If they start the work together but After 5 days A left the work . In how many days the total work would be finished ?

K alone can complete a work in 20 days and M alone can complete the same work in 30 days. K and M start the work together but K leaves the work after 5 days of the starting of work. In how many days M will complete the remaining work?