Home
Class 14
MATHS
Arjun started a task and left it after w...

Arjun started a task and left it after working for 2 days. Then, Bharath was called and he completed the task in 9 days. If Arjun alone had worked for 3 days, Bharath alone would have finished the remaining work in 6 days. In how many days can Arjun alone complete the task?

A

8 days

B

12 days

C

5 days

D

10 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem, let's denote the total work as 1 unit. We will also denote the work done by Arjun in one day as \( A \) and the work done by Bharath in one day as \( B \). ### Step 1: Work done by Arjun in 2 days Arjun works for 2 days, so the work done by Arjun in 2 days is: \[ \text{Work done by Arjun} = 2A \] ### Step 2: Work done by Bharath in 9 days After Arjun leaves, Bharath completes the remaining work in 9 days. Therefore, the work done by Bharath in 9 days is: \[ \text{Work done by Bharath} = 9B \] ### Step 3: Total work equation Since the total work is 1 unit, we can write the equation: \[ 2A + 9B = 1 \quad \text{(Equation 1)} \] ### Step 4: Work done if Arjun worked for 3 days If Arjun had worked for 3 days, the work done by him would be: \[ \text{Work done by Arjun in 3 days} = 3A \] Then, Bharath would finish the remaining work in 6 days, so: \[ \text{Work done by Bharath in 6 days} = 6B \] ### Step 5: Total work equation for this scenario The total work in this scenario can also be expressed as: \[ 3A + 6B = 1 \quad \text{(Equation 2)} \] ### Step 6: Solve the system of equations Now we have two equations: 1. \( 2A + 9B = 1 \) 2. \( 3A + 6B = 1 \) We can solve these equations simultaneously. Let's multiply Equation 2 by 3 to eliminate \( B \): \[ 9A + 18B = 3 \quad \text{(Equation 3)} \] Now, we can subtract Equation 1 from Equation 3: \[ (9A + 18B) - (2A + 9B) = 3 - 1 \] \[ 7A + 9B = 2 \quad \text{(Equation 4)} \] ### Step 7: Substitute to find \( B \) Now we can express \( B \) in terms of \( A \) using Equation 1: \[ 9B = 1 - 2A \implies B = \frac{1 - 2A}{9} \] Substituting \( B \) into Equation 4: \[ 7A + 9\left(\frac{1 - 2A}{9}\right) = 2 \] \[ 7A + 1 - 2A = 2 \] \[ 5A = 1 \implies A = \frac{1}{5} \] ### Step 8: Find \( B \) Now substitute \( A \) back to find \( B \): \[ B = \frac{1 - 2\left(\frac{1}{5}\right)}{9} = \frac{1 - \frac{2}{5}}{9} = \frac{\frac{3}{5}}{9} = \frac{1}{15} \] ### Step 9: Calculate days for Arjun to complete the task alone If Arjun can do \( A = \frac{1}{5} \) of the work in one day, then the number of days Arjun would take to complete the task alone is: \[ \text{Days for Arjun} = \frac{1}{A} = \frac{1}{\frac{1}{5}} = 5 \text{ days} \] ### Final Answer Arjun alone can complete the task in **5 days**.
Promotional Banner

Similar Questions

Explore conceptually related problems

A started a work and left after working for 4 days, then B was called and he finished the work in 18 days. If A left the work after working for 6 days then B would have finished the remaining work in 12 days. In how many days can each of them, working alone finish the whole work?

A can do a piece of work in 34 days. He worked for 14 days and then left. B completed the remaining work in 30 days. In how many days can B alone complete the work?

A and B can together complete a task 40 days. They worked together for 30 days and then left. A finished the remaining task in next 22 days. In how many days A alone can finish the task?

A alone can complete a task in 3 days and B alone can complete the same task in 6 days. In how manny days can A and B complete it together?

A and B can complete a task in 30 days, whereas A. B and C can complete the same task in 21 days. In how many days can C alone complete the task?

A and B can complete a task in 30 days, whereas A,B and C can complete the same task in 21 days. In how many days can C alone complete the task?

A can do a work in 12 days. When he had worked for 3 days, B joined him. If they complete the work in 3 more days, in how many days can B alone finish the work?