Home
Class 14
MATHS
A and B together can complete a task in ...

A and B together can complete a task in 1.2 days. However, if A works alone, completes half the job and leaves and 8 then B works alone and completes the rest of the work, it takes 2.5 days in all to complete the work. If B is more efficient than A, how many days would it have taken B to do the work by herself?

A

`1.5`

B

`1.8`

C

`2.0`

D

`2.2`

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will use the information given in the question about A and B's work rates and the total time taken to complete the task. ### Step 1: Define Variables Let: - A's time to complete the work alone = \( x \) days - B's time to complete the work alone = \( y \) days ### Step 2: Write the Work Rate Equation From the information that A and B together can complete the task in 1.2 days, we can express their combined work rate: \[ \frac{1}{x} + \frac{1}{y} = \frac{1}{1.2} \] This can be rewritten as: \[ \frac{1}{x} + \frac{1}{y} = \frac{5}{6} \] Multiplying through by \( xy \) gives: \[ y + x = \frac{5xy}{6} \quad \text{(Equation 1)} \] ### Step 3: Analyze the Work Done A completes half the job and then leaves. The time taken by A to complete half the job is: \[ \frac{x}{2} \text{ days} \] After A leaves, B completes the remaining half of the job. The time taken by B to complete half the job is: \[ \frac{y}{2} \text{ days} \] The total time taken to complete the work is given as 2.5 days: \[ \frac{x}{2} + \frac{y}{2} = 2.5 \] Multiplying through by 2 gives: \[ x + y = 5 \quad \text{(Equation 2)} \] ### Step 4: Solve the Equations Now we have two equations: 1. \( x + y = \frac{5xy}{6} \) 2. \( x + y = 5 \) From Equation 2, we can substitute \( x + y \) in Equation 1: \[ 5 = \frac{5xy}{6} \] Multiplying both sides by 6 gives: \[ 30 = 5xy \] Dividing by 5 gives: \[ xy = 6 \quad \text{(Equation 3)} \] ### Step 5: Substitute and Solve for x and y Now we can use Equation 2 and Equation 3 to find \( x \) and \( y \). From Equation 2: \[ y = 5 - x \] Substituting this into Equation 3: \[ x(5 - x) = 6 \] Expanding gives: \[ 5x - x^2 = 6 \] Rearranging gives: \[ x^2 - 5x + 6 = 0 \] ### Step 6: Factor the Quadratic Factoring the quadratic: \[ (x - 2)(x - 3) = 0 \] Thus, \( x = 2 \) or \( x = 3 \). ### Step 7: Find Corresponding y Values Using \( y = 5 - x \): - If \( x = 2 \), then \( y = 3 \). - If \( x = 3 \), then \( y = 2 \). ### Step 8: Determine the More Efficient Worker Since it is given that B is more efficient than A, we conclude: - If \( y = 3 \) (B takes 3 days), then \( x = 2 \) (A takes 2 days). - If \( y = 2 \) (B takes 2 days), then \( x = 3 \) (A takes 3 days). Thus, B must take 2 days to complete the work alone. ### Final Answer B would take **2 days** to complete the work by herself. ---
Promotional Banner

Similar Questions

Explore conceptually related problems

A and B together can complete a task in 12 days. However, if A works alone, completes half the job and leaves and then B works alone and completes the rest of the work, it takes 25 days in all to complete the work. If B is more efficient than A, how many days would it have taken B to do the work by herself?

A and B together can complete a piece of work in 4 days. If A alone can complete the same work in 12 days, in how many days can B alone complete that work ?

A and B together can complete a work in 35 days while A alone can complete the same work in 60 days. In how many days, B alone will be able to complete the same work?

A alone can complete a work in 6 days and B alone can complete the same work in 8 days. In how many days both A and B together can complete the same work?