Home
Class 14
MATHS
16 workers working 8 hours per day can d...

16 workers working 8 hours per day can demolish a building in 32 days. In how many days 24 workers working 12 hours per day can demolish the same building?

A

`frac 128 3` days

B

`frac 56 3` days

C

`frac128 9` days

D

`frac56 9` days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem, we can use the concept of work done, which can be expressed in terms of the number of workers, the number of days they work, and the number of hours they work each day. The relationship can be summarized with the formula: \[ M \times D \times H = W \] Where: - \( M \) = Number of workers - \( D \) = Number of days - \( H \) = Number of hours worked per day - \( W \) = Total work done (which we can consider as 1 for this problem since we are looking for the same building to be demolished) ### Step-by-Step Solution: 1. **Calculate the total work done by the first group of workers:** - Number of workers (M1) = 16 - Hours per day (H1) = 8 - Days (D1) = 32 Using the formula: \[ W = M1 \times D1 \times H1 = 16 \times 32 \times 8 \] 2. **Calculate the total work done:** \[ W = 16 \times 32 \times 8 = 4096 \text{ worker-hours} \] 3. **Set up the equation for the second group of workers:** - Number of workers (M2) = 24 - Hours per day (H2) = 12 - Days (D2) = ? Using the same formula: \[ W = M2 \times D2 \times H2 \] Substituting the known values: \[ 4096 = 24 \times D2 \times 12 \] 4. **Solve for D2:** \[ 4096 = 288 \times D2 \] \[ D2 = \frac{4096}{288} \] 5. **Calculate D2:** \[ D2 = \frac{4096 \div 16}{288 \div 16} = \frac{256}{18} = \frac{128}{9} \] ### Conclusion: Thus, the number of days required for 24 workers working 12 hours per day to demolish the same building is \( \frac{128}{9} \) days.
Promotional Banner

Similar Questions

Explore conceptually related problems

10 men working 8 hours day can do a work in 30 days. In how many days will 12 men working 4 hours a day take do the same work?

2 men each working 5 hour per day can finish a job in 12 days. How long will 4 men each working 2 hours per day take to finish the same job?

If 30men working 18h per day can reap a field in 32 days, in how many days can 36 men reap the field working 16h per day ?

4 men, each working 6 hours per day can build a wall in 9 days. How long will 6 men, each working 3 hours per day take to finish the same work?

8 men working for 9 hours a day can complete a piece of work in 20 days. In how many days can 7 men working for 10 hours a day complete the same piece of work?

If 20 men working 7 hours a day can do a piece of work in 10 days, in how many days will 15 men working 8 hours a day do the same piece of work?