Working together, A, B and C can complet...

Working together, A, B and C can complete a work in 36 days. If the efficiency of A, B and C are in the ratio 5: 6: 9, then B alone will complete the same work in:

A

120 days

B

100 days

C

60 days

D

90 days

Text Solution

Verified by Experts

The correct Answer is:
A
Promotional Banner

Similar Questions

Explore conceptually related problems

Working together A, B and C can complete a piece of work in 24 days. After working together for 4 days. C left the work. A and B completed the remaining work in 30 days. The number of days taken by C alone to complete the same work is:

A is twice as efficient as B and B is thrice as efficient as C. Working together, they can finish a certain work in 5 days. If A and C worked together for 5 days then B alone would complete the remaining work in .......

A and B together can complete a work in 35 days while A alone can complete the same work in 60 days. In how many days, B alone will be able to complete the same work?

P and Q together can complete a work in 20 days. If P alone can complete the same work in 36 days, then in how many days Q alone can complete the same work?

A can do (2)/(5) of a work in 6 days and B can do (2)/(3) of the same work in 12 days. A and B worked together for 6 days. C alone completed the remaining work in 8 days. A and C, working together, will complete the same work in:

B takes two times as long as (A + C) together to complete a work. C takes three times as much as (A + B) together to complete a work. If all the three, working together can complete the work in 36 days, then find the number of days A, B and C alone will take to complete this work.