A and B working together can complete a job in 30 days. The ratio of their efficiencies is 3 : 2. In how many days can the faster person complete the job?

A

50

B

30

C

40

D

60

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will follow these instructions: ### Step 1: Understand the given information A and B can complete a job together in 30 days, and the ratio of their efficiencies is 3:2. ### Step 2: Calculate the total work Since A and B together complete the job in 30 days, we can express the total work in terms of their combined efficiencies. Let the total work be represented in units. If A's efficiency is 3 units/day and B's efficiency is 2 units/day, then their combined efficiency is: \[ 3 + 2 = 5 \text{ units/day} \] Now, the total work done in 30 days is: \[ \text{Total Work} = \text{Efficiency} \times \text{Time} \] \[ \text{Total Work} = 5 \text{ units/day} \times 30 \text{ days} = 150 \text{ units} \] ### Step 3: Determine A's efficiency From the ratio of efficiencies (3:2), we know that A's efficiency is 3 units/day. ### Step 4: Calculate the time taken by A to complete the job alone To find out how many days A will take to complete the job alone, we can use the formula: \[ \text{Time} = \frac{\text{Total Work}}{\text{Efficiency of A}} \] Substituting the values we have: \[ \text{Time} = \frac{150 \text{ units}}{3 \text{ units/day}} = 50 \text{ days} \] ### Conclusion Thus, the faster person (A) can complete the job in **50 days**. ---
Promotional Banner

Similar Questions

Explore conceptually related problems

A and B can do a job together in 12days . A is 2 times as efficient as B . In how many days can B alones complete the work ?

Nirmit can do 2/3 rd of a job in 18 days. Kashish is twice as efficient as Nirmit. In how many days will kashish complete the job ?

A is twice as good a workman as B.If they work together,they can complete a job in 18 days.If A alone does the job,in how many days he will complete the job? 40backslash days b.27backslash days c.36backslash days d.4backslash days

A can do a job in 12 days and B can do the same job in 6 days, in how many days working together they can complete the job?

P can do a job in 12 days and Q can do the same job in 6 days, in how many days working together they can complete the job?