Home
Class 14
MATHS
X, Y and Z can do a piece of work in 30,...

X, Y and Z can do a piece of work in 30, 40and 50 days respectively. All three of them began the work together but Y left 4 days before completion of the work. In how many days was the work completed?

A

`660//47`

B

`640//47`

C

`680//47`

D

`665//47`

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem, we need to determine how many days it took for X, Y, and Z to complete the work together, given that Y left 4 days before the work was completed. ### Step-by-Step Solution: 1. **Determine the Work Rates of X, Y, and Z:** - X can complete the work in 30 days, so X's work rate is \( \frac{1}{30} \) of the work per day. - Y can complete the work in 40 days, so Y's work rate is \( \frac{1}{40} \) of the work per day. - Z can complete the work in 50 days, so Z's work rate is \( \frac{1}{50} \) of the work per day. 2. **Calculate the Combined Work Rate:** - The combined work rate of X, Y, and Z when they work together is: \[ \text{Combined Rate} = \frac{1}{30} + \frac{1}{40} + \frac{1}{50} \] - To add these fractions, we need a common denominator. The least common multiple (LCM) of 30, 40, and 50 is 600. - Convert each fraction: \[ \frac{1}{30} = \frac{20}{600}, \quad \frac{1}{40} = \frac{15}{600}, \quad \frac{1}{50} = \frac{12}{600} \] - Now add them: \[ \text{Combined Rate} = \frac{20 + 15 + 12}{600} = \frac{47}{600} \] 3. **Determine the Total Work Done:** - Let the total work be represented as 600 units (as we assumed). - Since Y leaves 4 days before the work is completed, let \( D \) be the total number of days taken to complete the work. - This means Y worked for \( D - 4 \) days. 4. **Calculate Work Done by Each Worker:** - Work done by X in \( D \) days: \( \frac{D}{30} \) - Work done by Y in \( D - 4 \) days: \( \frac{D - 4}{40} \) - Work done by Z in \( D \) days: \( \frac{D}{50} \) 5. **Set Up the Equation:** - The total work done by all three workers must equal 600 units: \[ \frac{D}{30} + \frac{D - 4}{40} + \frac{D}{50} = 1 \] - To eliminate the fractions, multiply through by 600 (the common denominator): \[ 20D + 15(D - 4) + 12D = 600 \] 6. **Simplify the Equation:** - Distributing the terms: \[ 20D + 15D - 60 + 12D = 600 \] - Combine like terms: \[ 47D - 60 = 600 \] - Add 60 to both sides: \[ 47D = 660 \] - Divide by 47: \[ D = \frac{660}{47} \approx 14.04 \text{ days} \] 7. **Conclusion:** - Since the number of days must be a whole number, we round up to the nearest whole number, which is 15 days. ### Final Answer: The work was completed in **15 days**.
Promotional Banner

Similar Questions

Explore conceptually related problems

A, B and C can complete a piec of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work in completed ?

A, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?

A can do a piece of work in 18 days and B in 12 days. They began the work together, but B left the work 3 days before its completion. In how many days, in all, was the work completed ?

A , B and C can do a piece of work in 24days,36 days and 108 days, respectively. They started the work together but A left 9 days after the start of the work and B left 3 days before the work was completed. For how many days did C work ?

A,B and C can complete a work in 10,12 and 15 days respectively.They started the work together.But A left the work 5 days before its completion.B also left the work 2 days after A left.In how many days was the work completed? 4 b.15 c.7 d.8