If 40 men working 12 hours a day can com...

If 40 men working 12 hours a day can complete a work in 8 days, then how many men working 4 hours a day can complete the same work in 16 days ?

A

60

B

50

C

54

D

45

Text Solution

Verified by Experts

The correct Answer is:
A