M can complete (3)/(4) part of a work in...

M can complete `(3)/(4)` part of a work in 12 days and N can complete `(2)/(7)` part of the same work in 8 days. In how many days will both complete `(11)/(14)` part of the total work?

A

8

B

9

C

7

D

6

Text Solution

Verified by Experts

Promotional Banner

Similar Questions

Explore conceptually related problems

A can do (1)/(4) part of a work in 21 days and B can do (1)/(4) part of a work in 7 days. In how many days will A and B complete the total work ?

A can do (13)/(56) part of a work in 111 days and B can do (43)/(56) part of a work in 111 days. In how many days will A and B complete the total work ?

A can make (1)/(3) part of a wall in 9 days and B can make (2)/(3) part of a wall in 9 days. In how many days will A and B complete the total work ?

A alone can complete a work in 10 days and B alone can complete the same work in 20 days. In how many days both 4 and B together can complete half of the total work?

12 men can complete a work in 16 days and 16 women can complete the same work in 12 days In how many days will 4 men and 8 women complete that work ?

Both X and Y together can complete a work in 12 days and Y alone can complete the same work in 30 days. In how many days will X alone complete the work?

A alone can complete a work in 12 days and B alone can complete the same work in 24 days. In how many days can A and B together complete the same work?